1501:14-4-03. Completion dates  


Latest version.
  • The operator shall specify, on each annual report and on the final report, the date on which surface mining operations were completed, terminated, or abandoned, if any such operations were completed, terminated, or abandoned, for each area of land affected during the reporting period.


Five Year Review (FYR) Dates: 9/14/2017 and 09/13/2022
Promulgated Under: 119.03
Statutory Authority: 1514.08
Rule Amplifies: 1514.02, 1514.03, 1514.08 , 1514.011
Prior Effective Dates: 3/24/75

Prior History: (R.C. 119.032 review dates: 07/14/2011 and 07/14/2016
Promulgated Under: 119.03
Statutory Authority: 1514.08
Rule Amplifies: 1514.011, 1514.02, 1514.03, 1514.08
Prior Effective Dates: 3/24/75 )