3745-104-30. Program three prevention program: pre-startup review  


Latest version.
  • (A) The owner or operator shall perform a pre-startup safety review for new stationary sources and for modified stationary sources when the modification of the covered process is significant enough to require a change in the process safety information.

    (B) The pre-startup safety review shall confirm that prior to the introduction of regulated substances to a process:

    (1) Construction and equipment is in accordance with design specifications;

    (2) Safety, operating, maintenance, and emergency procedures are in place and are adequate;

    (3) For new stationary sources, a process hazard analysis has been performed and recommendations have been resolved or implemented before startup; and modified stationary sources meet the requirements contained in management of change, rule 3745-104-29 of the Administrative Code.

    (4) Training of each employee involved in operating a process has been completed.