4901:1-22-02. Scope and application  


Latest version.
  • (A) The rules in this chapter are intended to do all of the following:

    (1) Make compliance within this chapter not unduly burdensome or expensive for any applicant in accordance with division (A) of section 4928.11 of the Revised Code.

    (2) Establish uniform nondiscriminatory, technology-neutral procedures for interconnecting distributed generators to distribution facilities in a manner that protects public and worker safety and system reliability .

    (3) Apply in the entire territory where commission-approved tariffs apply to those situations where an applicant seeks to physically connect distributed generation to, and operate it in parallel with, the EDU's distribution system.

    (4) Provide three review options for an applicant's request for interconnection with the EDU including simplified procedures, expedited procedures, and standard procedures.

    (B) Each EDU in the state of Ohio shall file uniform interconnection service tariffs for commission review and approval pursuant to division (A) of section 4928.11 of the Revised Code, that includes the procedures and technical requirements set forth in this chapter for interconnection service on a first-come, first-served basis.

    (C) The rules in this chapter shall not relieve any applicant from complying with all applicable federal, state, and local laws and ordinances.

Replaces: 4901:1-22-01


Effective: 07/10/2014
R.C. 119.032 review dates: 04/24/2014 and 06/24/2019
Promulgated Under: 111.15
Statutory Authority: 4928.06
Rule Amplifies: 4928.11
Prior Effective Dates: 9/18/00, 10/22/07