Ohio Administrative Code (Last Updated: January 12, 2021) |
4901:5 Division of Forecasting |
Chapter4901:5-37. Emergency Reporting by Electric Utilities |
4901:5-37-04. Sudden or unanticipated critical situation resulting in overloading transmission facilities
-
When sudden or unanticipated generation or transmission outages cause an overloading of an electric entity's facilities or interconnection circuits that operate at a nominal sixty hertz, that electric entity shall perform any or all of the following actions, as applicable:
(A) Interrupt service to customers served under interruptible tariffs or contracts.
(B) Interrupt service to firm service customers.
(C) Reduce voltage by not more than five per cent if the transmission system is isolated.
(D) Disconnect the overloaded facility or circuit.
The provisions of this rule do not apply to any municipal or cooperative unless the governor has declared an energy emergency under section 4935.03 of the Revised Code.
Five Year Review (FYR) Dates:
11/29/2017 and
11/29/2022
Promulgated
Under: 111.15
Statutory
Authority: 4935.03
Rule
Amplifies: 4935.03
Prior
Effective Dates: 09/18/2000, 02/27/2010,
11/08/2012
Prior History: (Effective:
11/08/2012
R.C.
119.032 review dates:
08/23/2012 and
11/30/2016
Promulgated
Under: 111.15
Statutory
Authority: 4935.03
Rule
Amplifies: 4935.03
Prior