4906-4-05. Electric grid interconnection  


Latest version.
  • (A) The applicant shall describe how the facility will be connected to the regional electric grid.

    (B) The applicant shall provide information on interconnection of the facility to the regional electric power grid.

    (1) The applicant shall provide information relating to their generation interconnection request, including interconnection queue name, number, date, and website.

    (2) The applicant shall provide system studies on their generation interconnection request. The studies shall include, but are not limited to, the feasibility study and system impact study.

Replaces: part of 4906-13-04, part of 4906-17-05


Effective: 12/11/2015
Five Year Review (FYR) Dates: 11/30/2020
Promulgated Under: 111.15
Statutory Authority: 4906.03, 4906.20
Rule Amplifies: 4906.03, 4906.04, 4906.06, 4906.10, 4906.13, 4906.20
Prior Effective Dates: 12/27/76, 7/7/80, 8/28/98, 12/15/03, 1/25/09, 5/7/09