4906-6-03. Filing of an accelerated application  


Latest version.
  • (A) At least five days prior to submitting an accelerated certificate application, the applicant shall request a case number and file a preapplication notification letter with the board. The preapplication notification letter shall include a general description of the project, an anticipated project schedule, and any requests for expedited processing. If an applicant fails to file a preapplication notification letter, and instead files its request for expedited processing along with its application, the expedited processing of its application will not begin until five days after its application is filed.

    (B) A letter of notification application shall be filed not less than ninety days before the planned commencement of construction. A letter of notification for which the applicant requests expedited processing shall be filed not less than twenty-eight days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-eight day requirement.

    (C) A construction notice shall be filed not less than ninety days before planned commencement of construction. A construction notice for which the applicant requests expedited processing shall be filed not less than twenty-one days before planned commencement of construction. For good cause shown, the applicant may request a shorter automatic approval date than the ninety or twenty-one day requirement.

Replaces: part of 4906-5-02


Effective: 12/11/2015
Five Year Review (FYR) Dates: 11/30/2020
Promulgated Under: 111.15
Statutory Authority: 4906.03
Rule Amplifies: 4906.03 , 4906.06
Prior Effective Dates: 12/27/76, 6/10/89, 8/28/98, 12/15/03, 1/25/09