4906-13-05 Financial data.
(A) The applicant shall state the current and proposed ownership status of the proposed facility, including site(s), rights-of-way, structures, and equipment. Such information shall include type of ownership.
(B) Capital and intangible costs. The applicant shall:
(1) Submit estimates of applicable capital and intangible costs for the various alternatives. The data submitted shall be classified according to federal energy regulatory commission uniform system of accounts prescribed by the public utilities commission of Ohio for utility companies, unless the applicant is not an electric light company, a gas company or a natural gas company as defined in Chapter 4905. of the Revised Code (in which case, the applicant shall file the capital and intangible costs classified in the accounting format ordinarily used by the applicant in its normal course of business).
(2) Compare the total costs per kilowatt with the applicant's similar facilities, and explain any substantial differences.
(3) Tabulate the present worth and annualized cost for capital costs and any additional cost details as required to compare capital cost of alternates ( using the start of construction date as reference date), and describe techniques and all factors used in calculating present worth and annualized costs.
(C) Operation and maintenance expenses. The applicant shall:
(1) Supply applicable estimated annual operation and maintenance expenses for the first two years of commercial operation. The data submitted shall be classified according to federal energy regulatory commission uniform system of accounts prescribed by the public utilities commission of Ohio for utility companies, unless the applicant is not an electric light company, a gas company or a natural gas company as defined in Chapter 4905. of the Revised Code (in which case, the applicant shall file the operation and maintenance expenses classified in the accounting format ordinarily used by the applicant in its normal course of business).
(2) Compare the total operation and maintenance cost per kilowatt with applicant's similar facilities and explain any substantial differences.
(3) Tabulate the present worth and annualized expenditures for operating and maintenance costs as well as any additional cost breakdowns as required to
compare alternatives, and describe techniques and factors used in calculating present worth and annualized costs.
(D) Delays. The applicant shall submit an estimate of the cost for a delay prorated to a monthly basis beyond the projected in-service date.
Effective: 12/11/2015
Five Year Review (FYR) Dates: 10/03/2014
CERTIFIED ELECTRONICALLY
Certification
11/30/2015
Date
Promulgated Under: 111.15
Statutory Authority: 4906.03
Rule Amplifies: 4906.06, 4906.03
Prior Effective Dates: 11/4/88, 8/28/98, 12/15/03
Document Information
- Effective Date:
- 12/11/2015
- File Date:
- 2015-11-30
- Last Day in Effect:
- 2015-12-11
- Five Year Review:
- Yes
- Rule File:
- 4906-13-05_FF_R_RU_20151130_1019.pdf
- Related Chapter/Rule NO.: (1)
- Ill. Adm. Code 4906-13-05. Financial data