4906-6-11 Construction of approved projects and notification of construction.
(A)Applicants who file accelerated certificate applications with the board may begin construction of projects reported in the applications after the date that automatic approval occurs or upon the approval by the board.
(B)Applicants shall file a notice with the board at least seven days in advance of beginning construction of the involved project if construction will begin on a different date from that contained in the application.
(C)Prior to commencement of construction, the applicant shall inform affected property owners and tenants of the nature of the project, specific contact information of applicant personnel who are familiar with the project, the proposed schedule for project construction and restoration activities, and a complaint resolution process. Notification to affected property owners and tenants shall be given at least seven days prior to work on the affected property.
(D)Applicants shall file a notice with the board within seven days following completion of the involved project.
4906-6-11 2
Replaces: part of 4906-5-02
Effective: 12/11/2015
Five Year Review (FYR) Dates: 11/30/2020
CERTIFIED ELECTRONICALLY
Certification
11/30/2015
Date
Promulgated Under: 111.15
Statutory Authority: 4906.03
Rule Amplifies: 4906.03, 4906.06
Prior Effective Dates: 12/27/76, 6/10/89, 8/28/98, 12/15/03, 1/25/09
Document Information
- Effective Date:
- 12/11/2015
- File Date:
- 2015-11-30
- Last Day in Effect:
- 2015-12-11
- Rule File:
- 4906-6-11_FF_N_RU_20151130_1002.pdf
- Related Chapter/Rule NO.: (1)
- Ill. Adm. Code 4906-6-11. Construction of approved projects and notification of construction