4906-13-02 Project description in detail and project schedule in detail.  

  • Text Box: ACTION: Final Text Box: DATE: 12/05/2003 2:30 PM

     

     

     

    4906-13-02                  Justification of needReview of need for proposed project.

     

     

     

    (A)   Need statement. An applicant for a certificate to site a an electric power generating facility under rules 4906-13-01 to 4906-13-07 of the Administrative Code this chapter shall provide a statement explaining the need for the proposed facility. The statement shall contain references of the most recent long-term forecast report, if applicable, including a listing of the factors upon which it relied to reach that conclusion and references to the most recent long-term forecast report (if applicable).

     

    (B)  Description of the proposed generation and associated facility alternatives.

     

    (1)  The applicant shall submit for each alternative:

     

    (a)    Type, number of units, and estimated net demonstrated capability, heat rate, annual capacity factor and hours of annual generation;.

     

    (b)   Land area requirement;.

     

    (c)    Fuel quantity and quality (i.e., ash, sulfur, and btu British thermal unit value);.

     

    (d)  A list of types of pollutant emissions; and.

     

    (e)    Water requirement, source of water, treatment, quantity of any discharge and names of receiving streams.

     

    (2)   The applicant shall submit a summary description of the major equipment.

     

    (3)   The applicant shall submit a brief description of the need for new transmission line(s) associated with the proposed facility.

     

    (C)  Project schedule.

     

    (1)   Schedule. The applicant shall provide a proposed schedule in bar chart format covering all applicable major activities and milestones, including:

     

    (a)   Acquisition of land and land rights;.

     

    (b)   Preparation of the application;.

     

     

     

     

    (c)   Submittal of the application for certificate;.

    (d)  Issuance of the certificate;.

    (e)   Preparation of the final design;.

    (f)  Construction of the facility; and.

    (g)   Placement of the facility in service.

    (2)   Delays. The applicant shall briefly describe the impact of critical delays on the eventual in-service date.

    Effective:                                12/15/2003

    R.C. 119.032 review dates:    09/30/2003 and 09/30/2008

    CERTIFIED ELECTRONICALLY

    Certification

    12/05/2003

    Date

    Promulgated Under:   111.15

    Statutory Authority:   4906.03

    Rule Amplifies:           4906.06, 4906.03

    Prior Effective Dates: 12/27/76, 7/7/80, 11/4/88,

    8/28/98

Document Information

Effective Date:
12/15/2003
File Date:
2003-12-05
Last Day in Effect:
2003-12-15
Five Year Review:
Yes
Rule File:
4906-13-02_FF_A_RU_20031205_1430.pdf
Related Chapter/Rule NO.: (1)
Ill. Adm. Code 4906-13-02. Project description in detail and project schedule in detail