4906-13-05 Financial data.  

  • Text Box: ACTION: Final Text Box: DATE: 12/05/2003 2:30 PM

     

     

     

    4906-13-05                  Financial data.

     

     

     

    (A)   The applicant shall state the current and proposed ownership status of the proposed facility, including sites site(s), rights-of-way, structures, and equipment. Such information shall include type of ownership.

     

    (B)  Capital and intangible costs. The applicant shall:

     

    (1)    Submit estimates of applicable capital and intangible costs for the various alternatives. The data submitted shall be classified according to FERC federal energy regulatory commission uniform system of accounts prescribed by the public utilities commission of Ohio for electric utility companies, unless the applicant is not an electric light company, a gas company or a natural gas company as defined in Chapter 4905. of the Revised Code (in which case, the applicant shall file the capital and intangible costs classified in the accounting format ordinarily used by the applicant in its normal course of business);.

     

    (2)   Compare the total costs per kW kilowatt with the applicant's similar facilities, and explain any substantial differences; and.

     

    (3)     Tabulate the present worth and annualized cost for capital costs and any additional cost details as required to compare capital cost of alternates (use using the start of construction date as reference date), and describe techniques and all factors used in calculating present worth and annualized costs.

     

    (C)  Operation and maintenance expenses. The applicant shall:

     

    (1)   Supply applicable estimated annual operation and maintenance expenses for the first two years of commercial operation. The data submitted shall be classified according to FERC federal energy regulatory commission uniform system of accounts prescribed by the public utilities commission of Ohio for utility companies, unless the applicant is not an electric light company, a gas company or a natural gas company as defined in Chapter 4905. of the Revised Code (in which case, the applicant shall file the operation and maintenance expenses classified in the accounting format ordinarily used by the applicant in its normal course of business);.

     

    (2)     Compare the total operation and maintenance cost per kWh kilowatt with applicant's similar facilities and explain any substantial differences; and.

     

    (3)     Tabulate the present worth and annualized expenditures for operating and maintenance costs as well as any additional cost breakdowns as required to compare alternatives, and describe techniques and factors used in calculating

     

     

     

    present worth and annualized costs.

    (D)   Delays. The applicant shall submit an estimate of the cost for a delay prorated to a monthly basis beyond the projected in-service date.

    Effective:                                12/15/2003

    R.C. 119.032 review dates:    09/30/2003 and 09/30/2008

    CERTIFIED ELECTRONICALLY

    Certification

    12/05/2003

    Date

    Promulgated Under:   111.15

    Statutory Authority:   4906.03

    Rule Amplifies:           4906.06, 4906.03

    Prior Effective Dates: 12/27/76, 7/7/80, 3/14/83,

    1/15/85, 8/28/98

Document Information

Effective Date:
12/15/2003
File Date:
2003-12-05
Last Day in Effect:
2003-12-15
Five Year Review:
Yes
Rule File:
4906-13-05_FF_A_RU_20031205_1430.pdf
Related Chapter/Rule NO.: (1)
Ill. Adm. Code 4906-13-05. Financial data