4906-5-08 Public notice of accepted, complete certificate applications.
(A) Prior to submitting
ana certificate application to the board, the applicant shall conduct at least one informational meeting open to the public to be held in the area in which the project is located. The applicant will give one public notice of the informational meeting in newspapers of general circulation in the project area. The information provided shall address the need for the project, the project schedule, the design of the facility, and other pertinent data.(B) After filing
a certifiedan accepted, complete application with the board, the applicant shall give at least two public notices of the proposed utility facility in newspapers of general circulation in those municipal corporations and counties in which the chief executive received service of a copy of the application pursuant to rule4906-5-054906-5-06 of the Administrative Code.(1) The initial public notice shall be published within seven days of the filing of the
certifiedaccepted, complete application and shall include the publication of a summary of thecertifiedaccepted, complete application. The notice shall occupy not less than one-fourth of a standard newspaper page, with letters not less thanten pointten-point type, shall bear the heading "notice of proposed major utility facility" in bold letters not less than one-fourth inch high orthirty pointthirty-point type, and shall contain the following information.(a) The name and a brief description of the proposed facility, including type and capacity;.
(b) A map showing the location and general layout of the proposed facility;.
(c) A list of officials served with copies of the
certifiedaccepted, complete application pursuant to rule4906-5-074906-5-06 of the Administrative Code;.(d) A list of public libraries that were sent paper copies or notices of availability of the accepted, complete application, and other readily accessible sites, (including any web sites and the address of the board,) where copies of the accepted, complete application are available for public inspection;.
(e) A statement, including the assigned docket number, that an application for a certificate to construct, operate, and maintain said facility is now pending before the board;.
(f) A statement setting forth the eight criteria listed in division (A) of section
4906.10 of the Revised Code used by the board to review an application;.
(g) Section 4906.07 of the Revised Code, including the time and place of the public hearing
; and.(h) Division (C) of section 4906.08 of the Revised Code, including the deadline for filing a notice of intervention or
motionpetition for leave to intervene as established by the board or administrative law judge.(2) The second public notice shall be published at least seven days but no more than twenty-one days before the public hearing. The notice shall be published with letters not less than
ten pointten-point type, shall bear the heading "notice of proposed major utility facility" in bold type not less thanone quarterone-fourth inch high orthirty pointthirty-point type and shall contain the following information:(a) The name and a brief description of the project;.
(b) A map showing the location and general layout of the proposed facility;.
(c) A statement, including the assigned docket number, that an application for a certificate to construct, operate, and maintain said facility is now pending before the
Ohio power sitingboard;.(d) The date, time, and location of the public hearing;.
(e) A statement that the public will be given an opportunity to comment on the proposed facility
; and.(f) A reference
asto the date of the first public notice.(3) At least thirty days before the public hearing, the applicant shall send a letter describing the facility to each property owner within the planned site or
right-of-wayInability or inadvertent failure tonotify the persons described in this subsection shall not constitute a failure togive public notice, provided substantial compliance with these requirementsis met.(C) Inability or inadvertent failure to notify the persons described in this rule shall not constitute a failure to give public notice, provided substantial compliance with these requirements is met.
Effective: 12/15/2003
R.C. 119.032 review dates: 09/30/2003 and 09/30/2008
CERTIFIED ELECTRONICALLY
Certification
12/05/2003
Date
Promulgated Under: 111.15
Statutory Authority: 4906.03
Rule Amplifies: 4906.06, 4906.03
Prior Effective Dates: 12/27/76, 6/10/89, 8/28/98
Document Information
- Effective Date:
- 12/15/2003
- File Date:
- 2003-12-05
- Last Day in Effect:
- 2003-12-15
- Five Year Review:
- Yes
- Rule File:
- 4906-5-08_FF_A_RU_20031205_1437.pdf
- Related Chapter/Rule NO.: (1)
- Ill. Adm. Code 4906-5-08. Public notice of accepted, complete certificate applications