3745-512-50 Construction certification.  

  • Text Box: ACTION: Final Text Box: DATE: 09/21/2016 10:45 AM

     

     

     

    3745-512-50                Construction certification.

     

     

     

    (A)For  each  engineered  component  at  the  facility,  the  owner  or  operator  shall demonstrate the following through a construction certification report:

     

    (1)Compliance with the facility design in the authorizing document.

     

    (2)The engineered component was installed in a manner that did not damage the engineered component or other engineered components.

     

    (3)Compliance  with  the  construction  requirements  in  this  chapter  for  the engineered component.

     

    (B)The construction certification report shall be signed and sealed by a professional engineer.

     

    (C)Each construction certification report shall include the following:

     

    (1)A  narrative  section  that  identifies  the  engineered  components  that  were constructed during the construction event, which shall include the following:

     

    (a) A comparison of each constructed engineered component to the design and any material or construction specification in the authorizing document and to the material and construction specifications in this chapter.

     

    (b) A summary of how construction was impacted by weather, equipment limitations, and any other difficulty that was encountered.

     

    (2)All alterations and alternatives that relate to the installation of any engineered component to be certified, and to be presented as follows:

     

    (a) A listing of all alterations previously concurred with and all alternatives previously approved.

     

    (b) All alteration requests which are proposed for concurrence. The alteration request shall conform to the requirements in 3745-512-55 of the Administrative Code.

     

    (3)The certification requirements for each engineered component constructed during the construction event in accordance with rules 3745-512-110 to 3745-512-460 of the Administrative Code and in accordance with any requirement in the authorizing document, which shall include the following:

     

    (a) Test results including all passing, failing, and inconclusive test results.

     

    (b) All survey information, which shall be signed and sealed by a professional surveyor.

     

     

    (4) A  demonstration  that  the  integrity  of  the  engineered  components  was maintained, including references to construction activity logs.

    (5) If any oil or gas well was plugged and abandoned, a demonstration of compliance with paragraph (C) of rule 3745-512-30 of the Administrative Code.

    (6) Verification that whenever equipment is used to test an engineered component, the equipment is properly calibrated in accordance with the manufacturer's recommendations and specifications.

    (7) A description of the experience, training, responsibilities in decision making, and any other qualifications of the personnel who provided construction oversight and conducted all of the testing on the engineered components for which the certification report is being submitted.

    (8) A certification statement and signature in accordance with rule 3745-500-50 of the Administrative Code.

    Effective:

     

    04/01/2017

    Five Year Review (FYR) Dates:

     

    04/01/2022

     

    CERTIFIED ELECTRONICALLY

     

     

    Certification

     

     

     

    09/21/2016

     

     

    Date

     

     

     

    Promulgated Under:

     

    119.03

     

    Statutory Authority:

    3734.02

     

    Rule Amplifies:

    3734.02

     

Document Information

Effective Date:
4/1/2017
File Date:
2016-09-21
Last Day in Effect:
2017-04-01
Rule File:
3745-512-50_PH_FF_N_RU_20160921_1045.pdf
Related Chapter/Rule NO.: (1)