3745-27-69. Applicability of requirements for a scrap tire monocell facility  


Latest version.
  • [Comment: The requirements for the permitting, construction, operation, closure, post-closure care, and financial assurance for a scrap tire monofill facility are specified in rules 3745-27-15 to 3745-27-17 and 3745-27-70 to 3745-27-75 of the Administrative Code.]

    (A) Applicability. A scrap tire monocell facility may be established and operated within the limits of waste placement of either of the following facilities as previously delineated in the applicable authorizing documents or as proposed in an application for permit to install a new facility or to expand an existing facility:

    (1) A sanitary landfill facility subject to Chapter 3745-27 of the Administrative Code.

    (2) An industrial solid waste landfill facility subject to Chapter 3745-29 of the Administrative Code provided the scrap tires to be received at the facility are "industrial solid wastes" as defined in rule 3745-29-01 of the Administrative Code.

    (B) Permit to install.

    (1) For the purposes of this rule, "contiguous monocell facility" means a scrap tire monocell facility which is contiguous to other cells, phases, and/or units of the sanitary or industrial solid waste landfill facility.

    (2) For the purposes of this rule, "noncontiguous monocell facility" means a scrap tire monocell facility which is not contiguous to other cells, phases, and/or units of the sanitary or industrial solid waste landfill facility such that it is physically separated from the other cells, phases, and/or units and has separate environmental control systems (leachate collection, surface water management, etc.).

    (3) An application for a permit to install as required by section 3734.77 of the Revised Code, shall be submitted to and approved by the director, before the establishment or modification of a scrap tire monocell facility is begun, as follows:

    (a) For a contiguous monocell facility, rule 3745-27-06 or 3745-29-06 of the Administrative Code, whichever is applicable, apply.

    (b) For a noncontiguous monocell facility, rule 3745-27-70 of the Administrative Code applies.

    (C) Other requirements. The construction, operation, closure, post-closure care, and financial assurance for a scrap tire monocell shall be as follows:

    (1) For a contiguous monocell facility, rules 3745-27-06 to 3745-27-20 of the Administrative Code, or Chapter 3745-29 of the Administrative Code, whichever is applicable, apply, except that the owner or operator may comply with following scrap tire monofill facility operational requirements in lieu of the equivalent provisions in rule 3745-27-19 or 3745-29-19 of the Administrative Code:

    (a) Paragraph (E) of rule 3745-27-75 of the Administrative Code(general requirements).

    (b) Paragraph (F) of rule 3745-27-75 of the Administrative Code(daily cover).

    (c) Paragraph (G) of rule 3745-27-75 of the Administrative Code(intermediate cover).

    (d) Paragraph (M) of rule 3745-27-75 of the Administrative Code(annual report).

    (2) For a noncontiguous monocell facility, rules 3745-27-70 to 3745-27-75 of the Administrative Code apply with the exception that the noncontiguous monocell facility shall be included within the ground water monitoring program for the sanitary or industrial solid waste landfill.


R.C. 119.032 review dates: 04/23/2014 and 04/23/2019
Promulgated Under: 119.03
Statutory Authority: 3734.72, 3734.77
Rule Amplifies: 3734.72, 3734.77
Prior Effective Dates: 3/1/1996, 8/15/2003

Prior History: (Eff 3-1-96; 8-15-03
Rule promulgated under: RC 119.03
Rule authorized by: RC 3734.72, 3734.77
Rule amplifies: RC 3734.72, 3734.77
R.C. 119.032 review dates: 10/30/2008 and 10/30/2013 )