3745-67-53. Containment  


Latest version.
  • If leachate or run-off from a pile is a hazardous waste, then either:

    (A)

    (1) The pile shall be placed on an impermeable base that is compatible with the waste under the conditions of treatment or storage;

    (2) The owner or operator must design, construct, operate, and maintain a run-on control system capable of preventing flow onto the active portion of the pile during peak discharge from at least a twenty-five-year storm;

    (3) The owner or operator must design, construct, operate, and maintain a run-off management system to collect and control at least the water volume resulting from a twenty-four-hour, twenty-five-year storm; and

    (4) Collection and holding facilities (e.g., tanks or basins) associated with run-on and run-off control systems must be emptied or otherwise managed expeditiously to maintain design capacity of the system; or

    (B)

    (1) The pile shall be protected from precipitation and run-on by some other means; and

    (2) No liquids or wastes containing free liquids may be placed in the pile.


Eff 4-15-81; 1-7-83; 5-29-85 (Emer.); 8-29-85
Rule promulgated under: RC Chapter 119.
Rule amplifies: RC 3734.12