3745-91-07. Requirements for submittal letter  


Latest version.
  • The submittal letter shall:

    (A) Be signed by the responsible public official or, for a privately-owned project, the owner or his authorized representative;

    (B) Be addressed to the division of drinking and ground waters at the applicable district office;

    (C) Specifically request that the Ohio environmental protection agency review the plans for approval;

    (D) Accompany the plan drawings and other documents required by this chapter of the Administrative Code when they are submitted for review;

    (E) Include the name, mailing address, and telephone number of the owner or other person with whom contact can be made if further information is required.


Five Year Review (FYR) Dates: 10/26/2015 and 10/26/2020
Promulgated Under: 119.03
Statutory Authority: 6109.04
Rule Amplifies: 6109.03, 6109.04 , 6109.07
Prior Effective Dates: 11/26/80

Prior History: (R.C. 119.032 review dates: 03/17/2011 and 03/17/2016
Promulgated Under: 119.03
Statutory Authority: 6109.04
Rule Amplifies: 6109.03, 6109.04, 6109.07
Prior Effective Dates: 11/26/80 )