3745-50-36. Annual hazardous waste permit fees
-
(A) On each anniversary of the date of issuance of the hazardous waste facility installation and operation permit and of any subsequent renewal permits, the owner or operator of that facility shall pay to the director an annual permit fee. Annual permit fees totaling forty thousand dollars or more for any one facility may be paid on a quarterly basis, with the first quarterly payment each year being due on the anniversary of the date of issuance of the hazardous waste facility installation and operation permit and of any subsequent renewal permits.
(B) The annual permit fee shall be determined for each permit holder in accordance with the following schedule:
Type of unit
Type of facility
Fee
Storage facility using:
Containers
On-site, off-site, and satellite
$500
Tanks
On-site, off-site, and satellite
500
Waste pile
On-site, off-site, and satellite
3,000
Surface impoundment
On-site and satellite
8,000
Surface impoundment
Off-site
10,000
Disposal facility using:
Deep well injection
On-site and satellite
$15,000
Deep well injection
Off-site
25,000
Landfill
On-site and satellite
25,000
Landfill
Off-site
40,000
Land application
On-site and satellite
2,500
Land application
Off-site
5,000
Surface impoundment
On-site and satellite
10,000
Surface impoundment
Off-site
20,000
Treatment facility using:
Tanks
On-site, off-site, and satellite
$700
Surface impoundment
On-site and satellite
8,000
Surface impoundment
Off-site
10,000
Incinerator
On-site and satellite
5,000
Incinerator
Off-site
10,000
Other forms of treatment
On-site, off-site, and satellite
1,000
(C) For a hazardous waste facility subject to the payment of an annual permit fee under paragraph (A) of this rule, additional payments for multiple units of the same method of storage, treatment, or disposal, or for individual units that are used for both storage and treatment shall not be made. A facility using more than one method of storage, treatment, or disposal is subject to the permit fee indicated by the schedule for each such method.
(D) Payment shall not be made for the portion of an annual permit fee that would apply to a hazardous waste management unit for which a permit has been issued but for which construction has not yet commenced. Once construction has commenced, payment shall be prorated on a daily basis, computed upon the number of days from the commencement of construction until the next anniversary date when the payment of the annual fee is due.